On May 12 we received the building permit, so May 14 the construction
crew from TJ Painting and Contracting started the demolition.
Construction is estimated to take about 4 months and it’s amazing what
they’ve gotten done already!
Before construction beganWithout the flooringCeiling and walls coming out
Ceiling, insulation, floor all removed and walls open
New ceiling with rooms and plumbing marked on the floor
Spray foam insulation and furnaces in the rafters
Plumbing being added to the trenches
Drilling into the concrete for all of the drains and plumbing